Saturday, September 24, 2011

Day 102

• Ceiling joist framing in the ground floor
• More plastering and installation of PVC water pipes

Photobucket


Photobucket


Photobucket


Photobucket



Wednesday, September 14, 2011

Day 92

• Completed cement pouring in the ground floor
• Ongoing plastering
• Support posts for the fence


Photobucket


Photobucket


Photobucket


Photobucket



Monday, September 12, 2011

Day 90

Cement pouring completed on ground floor

No pictures!

Saturday, September 10, 2011

Day 88 (w/ Mom & Dad)

• Electrical conduit bending for ground floor
• CHB laying for kitchen and laundry area partition

Photobucket


Photobucket


Photobucket


Photobucket


Photobucket


Photobucket



Thursday, September 8, 2011

Day 85

• Cement pouring on driveway and terrace
• Installation of concrete wire mesh reinforcement on ground floor

Day 85


Day 85


Day 85


Day 85



Wednesday, September 7, 2011

Day 84

• Earthworks: filling and compacting
• Crushed gravel on ground floor
• Excavation for septic tank ongoing


Photobucket


Photobucket


Photobucket


Photobucket



Thursday, September 1, 2011

Day 78

Roof installed
• Ground floor plastering ongoing

Day 78


Day 78


Day 78


Day 78